The Chengdu-Lanzhou Railway's C L Z Q - 7 section spans a total length of 7.317 kilometers, with the starting and ending mileages of DK124+042.985 to DK131+360 (right track YDK126+539.661 to YDK131+508). The contract price amounts to 1.08 billion yuan. The project is located in Jushui Town, Anxian County, Sichuan Province. It is a Class I national railway, with a design speed of 200 kilometers per hour and an infrastructure speed target of 250 kilometers per hour. The commencement date was December 13, 2012, and the completion date is September 12, 2017. The total construction duration is 57 months.